Executive design, safety coordination in the design phase and functional adjustment works on the North-West floodway between Senago (MI) and Settimo Milanese (MI).

Descrizione lavoro:

– Work on the floodway for a segment approximately 12 km long;
– Floodway reshaping works widening the section for a length of ml 5,100;
– Lining with prefabricated reinforced cement slabs;
– Minor works such as bridges, by-passes, links with the existent hydraulic network.

Work in association with: I.C.G. S.r.l.

Committente:
PROVINCIA DI MILANO

Anno di realizzazione:
2014-2017